Problem:Earned-value analysis. A project budget calls for the following expenditures:TaskDateBudgeted

Problem:Earned-value analysis. A project budget calls for the following expenditures:TaskDateBudgeted AmountBuild formsApril 1$10,000Pour foundationApril 1$50,000May 1$100,000Frame wallsMay 1$30,000June 1$30,000Remaining tasksJuly 1 and beyond$500,000
Define each term in your own words, calculate these values for the above project, and show your work:

  1. Budgeted cost baseline (make a graph illustrating this one)
  2. Budget at completion (BAC)
  3. Planned value (PV) as of May 1
  4. Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
  5. SV as of May 1.
  6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
  7. Schedule performance index (SPI)
  8. Cost performance index (CPI)
  9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
  10. Estimate at completion (EAC)

Text

Title: Project Management 

Subtitle: https://opentextbc.ca/projectmanagement/ 

Authors: Adrienne Watt 

Publisher: BCcampus Open Education 

Publication Date: 2019 

Edition: 2nd Edition

Share This Post

Email
WhatsApp
Facebook
Twitter
LinkedIn
Pinterest
Reddit

Order a Similar Paper and get 15% Discount on your First Order

Related Questions

Please upload your picture to this site. Please describe picture

  Please upload your picture to this site. Please describe picture and tell the class why you think this is a good example of public health. Purpose: Many times we overlook the evidence and importance of public health efforts in our communities, however, the evidence is all around us. Public

“Social Institutions” and “Living Conditions: Cultural Analysis

4 to 5 page papers (plus charts and graphs) are required for this course. The papers must be typed or word processed, one-and-one-half- or double-spaced with one-inch margins, minimum 10-point type. (Using Times or Times New Roman font, 10-point type, you can easily put 2,000 words in a 4-5 page

Personal Reflection Question – Total Marks 20 (max word limit

   Personal Reflection Question – Total Marks 20 (max word limit- 300) 1. Imagine yourself as an entrepreneur of ABC LTD. ABC Ltd is a new startup dealing with high-end -organic products ( FMCG). The firm has completed 5 successful years. Based on    the given scenario- answer the following questions

PICO four-please review Nursing Assignment Help

PICO four-please review Expert Solution Preview Introduction: As a medical professor, my role is to design college assignments and assessments for medical college students. I also conduct lectures, evaluate student performance, and provide feedback through examinations and assignments. The following is an answer to the content provided. Answer: PICO is

200 words 1 reference within 5 years 1. Noemi Nurses

200 words 1 reference within 5 years 1.  Noemi Nurses and other health professionals have increasingly engaged in proxy reports to promote a high quality of life for children and infants whose age prevents them from reliably self-reporting. They must acknowledge that a patient’s incompetence does not influence their obligation

asapnursing PLEASE READ THE ENTIRE CASE STUDI BEFORE ANSWERING THE

asapnursing PLEASE READ THE ENTIRE CASE STUDI BEFORE ANSWERING THE QUESTIONS. REFERENCES HAVE TO BE APA STILL AND CAN NOT USE REFERENCES OLDER THEN 5 YEARS OLD. You are required to answer all the DISCUSSION QUESTIONS listed below in each domain. DOMAIN: HISTORY1a) Identify two (2) additional questions that were

Not only do managers oversee functional processes in company, they

Not only do managers oversee functional processes in company, they also have to manage people. Human Resources (HR) is the primary way that companies manage people and HR assists managers with areas such as hiring, training, employment law, performance management, employee benefits, and compensation. They also use organizational behavior principles to

People that use health services are divided into 4 categories:

People that use health services are divided into 4 categories: Age, gender, social classes, and social psychological factors. Very young and elderly people are more likely to utilize health services. Women are more likely to use health services compared to men. This is because women usually need health services more

Reflecting on what you have learned about the social determinants

Reflecting on what you have learned about the social determinants of health, SDOH, how can nurses work collaboratively with physicians and other health care professionals to improve primary care, reduce overutilization and improve underutilization of healthcare services? Include in your response how fostering an environment of diversity and cultural awareness

Instructions In 2–4 pages, your assignment must address the following:

Instructions In 2–4 pages, your assignment must address the following:  Describe the five variables that should be addressed in an expatriate performance management system. Analyze the elements within each of the five variables that should be considered in the performance management system. Evaluate the challenges with conducting performance evaluations  for

I need experienced and professional computer science writers who have

I need experienced and professional computer science writers who have worked on database work before. Please chat with me in case you are good enough to handle it. I need to deal with the writer and not middlemen. The work needed within 24 hours time frame  NB:  Use oracle developer 

Use the appropriate descriptive statistics from W2 Project or run

Use the appropriate descriptive statistics from W2 Project or run new descriptive statistics for Recall1 using Microsoft Excel. Assuming that the sample statistics you computed are exactly equivalent to the corresponding population parameters, and using the formula X = (±z)(sd) + M (see below) identify the following: The exact score

Write a letter to someone who is important to you,

Write a letter to someone who is important to you, such as a close friend or family member, about one of the issues we studied in our most recent modules: immigration policy, police reform, or reproductive rights and how those issues may impact their civil rights or civil liberties. 1) Explain

**PLEASE READ – Notes for this week should be recorded

**PLEASE READ – Notes for this week should be recorded for only (1)Privilege 101: A Quick and Dirty Guide  (2)Privilege Checklists – You do not have to mention each checklist separately. One reaction to all of them is OK (3)White Privilege: Unpacking the Invisible Knapsack (4)Power, Privilege, and Oppression .** Other readings will be covered

Read the Sport Obermeyer Case Study in the Simchi-Levi et

Read the Sport Obermeyer Case Study in the Simchi-Levi et al. text. Submit a response to each of the end-of-case discussion questions. Each question must be answered thoroughly, and responses must be supported by the concepts introduced in the Learn materials. Each question/answer must be delineated under a heading in

An enterprise resource planning (ERP) system is a set of

 An enterprise resource planning (ERP) system is a set of business applications that are integrated to provide support for core business process activities. Core business process activities may include actions around manufacturing production, logistics, sales, marketing, finance, accounting, human resources, and others. Implementation of an ERP system aids the organizational

· Using APA format write 1-2 paragraphs answering the questions

·  Using APA format write 1-2 paragraphs answering the questions below-  ·  Use the questions as a title for each paragraph.  ·  Please use the websites provided in addition to any other journals,   websites, or scholarly articles.  -Create a 7-slide PowerPoint to present to the class.  Slide1: Introduction Slide2: What